How long does an orangery take to build?

Orangery with new brick piers and lantern replacing an old conservatory

From first visit to finished room, most orangeries take three to five months. Around half of that is design, approvals and manufacture before anyone starts digging.

How long is the design stage?

Survey, drawings and a fixed quote usually take two to three weeks. Structural calculations and the building control application add one to two weeks and can run alongside frame manufacture.

How long does planning take?

Councils aim to decide householder applications within eight weeks. Listed building consent takes a similar time, and sensitive sites can take longer. Permitted development projects skip this stage.

How long are frames and lanterns on order?

uPVC and aluminium frames typically take three to five weeks. Painted hardwood joinery takes eight to twelve weeks, which is why timber orangeries need the earliest decisions.

How long is the build on site?

Six to ten weeks for a typical room: about two weeks for foundations and base, two for masonry and steel, one to two for the roof and lantern, one for glazing and two to three for electrics, plastering, screed and finishes.

What causes delays?

Wet weather during groundworks, unexpected drains, late design changes and long lead times on matching brick. A fixed design and an early brick order prevent most of them.

Preferred source: if you found this useful, add Orangeries UK as a preferred source on Google.

Next: get a guide price, see orangery prices or browse orangery types.

Ready to plan your orangery?

Book a free design visit or get a guide price in under a minute.

Get a guide price Call 0800 088 6248
Call usGet a quote